March 9th - Framing continues - Views shown are the lounge area and the proshop.
March 2nd - Framing started.
February 8th - Final pouring of the main floor.
January 15th - Steel joists are finished. Began installation of the main floor (Concrete on steel).
December 21st - After a long weather delay, steel beams continue to be placed.
November 30th - Back fill and begin installing steel girders & floor system
FYI - 1/2 the basement is designed for "future" cart storage, carts can be removed if a flood comes. The other 1/2 is crawl space only.