Highwood Golf & Country Club
HomeMembershipTournamentsPro ShopClubhouseCourseContact UsEmploymentMember Login

Our new clubhouse

  
March 9th - Framing continues - Views shown are the lounge area and the proshop.

  
March 2nd - Framing started.

  
February 8th - Final pouring of the main floor.

  
January 15th - Steel joists are finished.  Began installation of the main floor (Concrete on steel).

  
December 21st - After a long weather delay, steel beams continue to be placed.

  
November 30th - Back fill and begin installing steel girders & floor system
FYI - 1/2 the basement is designed for "future" cart storage, carts can be removed if a flood comes.  The other 1/2 is crawl space only.

  
November 18th - Final day for foundation pouring.

  
October 30th, 2009 - Footings being poured

     
October 22nd, 2009 - Pro Shop Demolition


  

 
Highwood Golf & Country Club
 Copyright © 2008 HIGHWOOD Golf & Country Club